User stories
1. Control algorithm.
2. The developer have to optimize the processing speed to provide a better product experience.
3. The researcher must be able to change the vehicle mode to realize different tests.
4. The RICM must master the different technologies to be able to do the project.
5. The researcher must be able to consult in real time the car's information to make changes if needed.
6. The RICM want the car works in order to start the project.
Product backlog
User story | Priority | Time | Actors | |
---|---|---|---|---|
1 | The RICM want the car works in order to start the project. | 34 | 1 week | |
2 | The RICM must master the different technologies to be able to do the project. | 34 | all time | all |
3 | The researcher must be able to consult in real time the car's information to make changes if needed. | 21 | 2 weeks | |
4 | The developer have to optimize the processing speed to provide a better product experience. | 21 | 1 week | |
5 | Control algorithm. | 13 | ||
6 | The researcher must be able to change the vehicle mode to realize different tests. | 8 | 3 weeks |