Difference between revisions of "Fiche - Tachymètre"
Jump to navigation
Jump to search
Regis.Ramel (talk | contribs) |
Regis.Ramel (talk | contribs) |
||
Line 1: | Line 1: | ||
− | = |
+ | = Project team = |
* MACE Quentin |
* MACE Quentin |
||
* NOUGUIER Thibaut |
* NOUGUIER Thibaut |
||
Line 5: | Line 5: | ||
* Tuteur : Olivier Gattaz |
* Tuteur : Olivier Gattaz |
||
− | = |
+ | = Project progress = |
− | == |
+ | == Week 1 : 11/01 - 17/01 == |
+ | * Choose of the project |
||
− | * Choix du projet |
||
− | * |
+ | * Presentation of Cohorte by Olivier Gattaz and Bassem Debbabi |
− | == |
+ | == Week 2 : 18/01 - 24/01 == |
+ | * Discover of the project environment |
||
− | * Découverte du projet |
||
− | * Installation |
+ | * Installation of Cohorte tools |
+ | * Definition of functional and non-functional requirements |
||
− | * Détermination des exigences fonctionnelles et non fonctionnelles |
||
+ | * Writing of the SRS |
||
− | * Écriture du [[SRS_-_Tachymètre | '''SRS''']] |
||
− | == |
+ | == Week 3 : 25/01 - 31/01 == |
− | * |
+ | * Cohorte tutorial done |
+ | * Realisation of UML diagrams |
||
− | * Réalisation des diagrammes [[UML_-_Tachymètre | '''UML''']] |
||
− | == |
+ | == Week 4 : 01/02 - 07/02 == |
− | * |
+ | * Meeting at Isandlatech with Olivier Gattaz |
− | * |
+ | * Study of the Doppler effect |
+ | * Simulations of speed calculations based on the frequency |
||
− | * Simulation de calcul de vitesse à partir d'un angle et d'une fréquence |
||
− | * |
+ | * Starting the project with Cohorte |
− | == |
+ | == Week 5 : 08/02 - 14/02 == |
− | * |
+ | * Meeting at Isandlatech with Olivier Gattaz |
+ | * Working on the component diagram |
||
− | * Travail sur le diagramme composant |
||
+ | * Working on the web client’s structure |
||
− | * Travail sur la structure du client web |
||
+ | * Definition of processed data and synthetic data |
||
− | * Discussion sur les données élaborées et synthétiques |
||
+ | * Tasks repartition |
||
− | * Répartition des tâches et estimation des temps de travail |
||
+ | * Working on use case |
||
− | * Travail sur les cas d'utilisation |
||
− | == |
+ | == Week 6 : 15/02 - 21/02 == |
− | * |
+ | * Meeting at Isandlatech with Olivier Gattaz |
− | * |
+ | * Working on Cohorte : Specification of components an application’s structure |
+ | * Working on wiring the sensor |
||
− | * Travail sur le cablage du capteur |
||
− | * |
+ | * Working on connecting the Raspberry Pi (many fails) |
+ | Problems : |
||
− | Problèmes rencontrés : |
||
− | * Confusion |
+ | * Confusion between our Raspberry and Isandlatech’s |
− | * |
+ | * SD carte troubleshooting, impossible to install raspbian |
− | == |
+ | == Week 7 : 22/02 - 28/02 == |
+ | * Holidays |
||
− | * Vacances |
||
− | * |
+ | * Tries to install raspbian on the Raspberry (fail) |
− | == |
+ | == Week 8 : 29/02 - 06/03 == |
− | * Installation |
+ | * Installation of raspbian on the Raspberry |
+ | * Working on the 7th march presentation |
||
− | * Travail sur la présentation du 7 mars |
||
+ | Problems : |
||
− | Problèmes rencontrés : |
||
+ | * An Arduino is needed to acquire measures from the HB100 |
||
− | * Nécessité d'utiliser un Arduino pour faire l'acquisition des mesures du HB100 |
||
− | == |
+ | == Week 9 : 07/03 - 13/03 == |
+ | * 7th march presentation |
||
− | * Soutenance de milieu de projet |
||
− | * |
+ | * Working on the web interface |
− | * |
+ | * Meeting at Isandlatech with Olivier Gattaz |
− | * |
+ | * Working on the connection Raspberry – Arduino |
− | * |
+ | * Working on the connection Arduino – HB100 |
− | * |
+ | * Connexion between Arduino and a PC established |
+ | * Working on returning and displaying measures from the sensor |
||
− | * Travail sur le renvoi et l'affichage des valeurs captées par le HB100 |
||
− | == Semaine 10 : 14 Mars - 20 Mars == |
||
⚫ | |||
− | * Travail sur l'élaborateur des données |
||
− | * Travail sur le client web |
||
− | * Travail sur les composants du Raspberry (cache, sender) |
||
⚫ | |||
− | * Test en voiture autour de Isandlatech |
||
− | * Atelier bricolage pour créer un tube pour diriger la mesure |
||
− | * Travail sur les composants Cohorte |
||
− | Problèmes rencontrés : |
||
− | * Impossible d'obtenir des mesures de vitesse supérieures à 25km/h |
||
− | == |
+ | == Week 10 : 14/03 - 20/03 == |
⚫ | |||
− | * Prise de conscience générale de la nécessité d'un circuit d'amplification du signal |
||
+ | * Working on the data process |
||
− | * Travail sur la connexion entre les composants Cohorte |
||
+ | * Working on the web interface |
||
− | * Travail sur le rapport |
||
+ | * Working on the Raspberry components |
||
− | Problèmes rencontrés : |
||
⚫ | |||
− | * Problème d'intégration des composants Cohorte dans l'application |
||
+ | * Tests with a car around Isandlatech |
||
+ | * Creation of a tube to lead the sensor waves |
||
+ | * Working on Cohorte components |
||
+ | Problems : |
||
+ | * Impossible to get speed measures over than 25 km/h |
||
− | == |
+ | == Week 11 : 21/03 - 27/03 == |
+ | * Discover of the need to build an amplification circuit |
||
− | * Travail sur la connexion entre les composants Cohorte |
||
+ | * Working on the connection between the different Cohorte components |
||
− | * Travail sur la transmission d'une donnée du capteur jusqu'au serveur |
||
+ | * Working on the report |
||
− | * Travail sur le rapport |
||
+ | Problems : |
||
− | * Travail sur les composants échantillonneur et élaborateur |
||
+ | * Problems with the integration of Cohorte components in the application |
||
− | Problèmes rencontrés : |
||
− | * Problèmes avec les dépendances des modules |
||
− | == |
+ | == Week 12 : 28/03 - 03/04 == |
+ | * Working on connecting between the different Cohorte components |
||
+ | * Working on transmitting data from the sensor to the server |
||
+ | * Working on the report |
||
+ | * Working on “Échantillonneur” and “Élaborateur” components |
||
+ | Problems : |
||
+ | * Problems with the dependances between components |
||
+ | |||
+ | |||
+ | == Week 13 : 04/04 - 06/04 == |
Revision as of 08:58, 4 April 2016
Project team
- MACE Quentin
- NOUGUIER Thibaut
- RAMEL Régis
- Tuteur : Olivier Gattaz
Project progress
Week 1 : 11/01 - 17/01
- Choose of the project
- Presentation of Cohorte by Olivier Gattaz and Bassem Debbabi
Week 2 : 18/01 - 24/01
- Discover of the project environment
- Installation of Cohorte tools
- Definition of functional and non-functional requirements
- Writing of the SRS
Week 3 : 25/01 - 31/01
- Cohorte tutorial done
- Realisation of UML diagrams
Week 4 : 01/02 - 07/02
- Meeting at Isandlatech with Olivier Gattaz
- Study of the Doppler effect
- Simulations of speed calculations based on the frequency
- Starting the project with Cohorte
Week 5 : 08/02 - 14/02
- Meeting at Isandlatech with Olivier Gattaz
- Working on the component diagram
- Working on the web client’s structure
- Definition of processed data and synthetic data
- Tasks repartition
- Working on use case
Week 6 : 15/02 - 21/02
- Meeting at Isandlatech with Olivier Gattaz
- Working on Cohorte : Specification of components an application’s structure
- Working on wiring the sensor
- Working on connecting the Raspberry Pi (many fails)
Problems :
- Confusion between our Raspberry and Isandlatech’s
- SD carte troubleshooting, impossible to install raspbian
Week 7 : 22/02 - 28/02
- Holidays
- Tries to install raspbian on the Raspberry (fail)
Week 8 : 29/02 - 06/03
- Installation of raspbian on the Raspberry
- Working on the 7th march presentation
Problems :
- An Arduino is needed to acquire measures from the HB100
Week 9 : 07/03 - 13/03
- 7th march presentation
- Working on the web interface
- Meeting at Isandlatech with Olivier Gattaz
- Working on the connection Raspberry – Arduino
- Working on the connection Arduino – HB100
- Connexion between Arduino and a PC established
- Working on returning and displaying measures from the sensor
Week 10 : 14/03 - 20/03
- Working on the transmission of data between the Arduino and the Raspberry
- Working on the data process
- Working on the web interface
- Working on the Raspberry components
- Meeting at Isandlatech with Olivier Gattaz
- Tests with a car around Isandlatech
- Creation of a tube to lead the sensor waves
- Working on Cohorte components
Problems :
- Impossible to get speed measures over than 25 km/h
Week 11 : 21/03 - 27/03
- Discover of the need to build an amplification circuit
- Working on the connection between the different Cohorte components
- Working on the report
Problems :
- Problems with the integration of Cohorte components in the application
Week 12 : 28/03 - 03/04
- Working on connecting between the different Cohorte components
- Working on transmitting data from the sensor to the server
- Working on the report
- Working on “Échantillonneur” and “Élaborateur” components
Problems :
- Problems with the dependances between components