Revision as of 14:20, 15 February 2016
Subject: Sonotone
Supervisors:
- Jérôme Maisonasse
Students:
- HATTINGUAIS Julian (RICM4)
- LECORPS Germain (RICM4)
- VOUTAT Manuel (RICM4)
Subject summary
Week 1 (January 18th - January 24th)
Objectives
Documentation on sonotone (learning process)
Study of software already used for hearing aid (learning process)
Learning of a new programmation language : python with NUMPY and SCYPI modules
Work done
Assembling the needed documentation
A few prototypes and little program on Fourier transform and signal edition
Problems faced
Difficulties to apply a filter to an audio signal in python
Week 2 (January 25th - January 31th)
Objectives
Prototype of an equalizer filter (3 weeks job)
Learning of new concepts in Signal Processing
Work done
More prototypes about filters and signals edition
Learning of the concepts we need for peacking filter and z-transform
Problems faced
Difficulties to apply our theoritical knowledge of a numerical processing
Week 3 (February 1st - February 7th)
Objectives
Prototype of an equalizer filter (3 weeks job)
Apply a gain on a specific frequency (by peaking filter)
Work done
prototype of a peaking filter which works and which is performant
Problems faced
Difficulties to apply the gain the correct frequency
Week 4 (February 8th - February 14th)
Objectives
Prototype of an equalizer filter (3 weeks job)
Graphic equalizer
Work done
Graphic equalizer done!
Week 5 (February 15th - February 21st)
Objectives
Prototype d'un equaliseur paramétrique
Work done
Problems faced
Week 6 (February 29th - March 6th)
Objectives
Filtrage en temps réel
Work done
Problems faced
Week 7 (March 7th - March 13th)
Objectives
Filtrage en temps réel
Work done
Problems faced
Week 8 (March 14th - March 20th)
Objectives
Filtrage en temps réel
Work done
Problems faced
Week 9 (March 21st - March 27th)
Objectives
Filtrage en temps réel/GUI (Design, IHM…)
Work done
Problems faced
Week 10 (March 28th - April 3rd)
Objectives
GUI (Design, IHM…)