=Progress of the project=
=Progress of the project=


The project started January 14th, 2013.
The project started January 21th, 2013.


==Week 1 (01/21)==
==WEEK 1: from January 14th to January 20th==
*Writing Score Report and SRS


==Week 2 (01/28)==
*Finishing [http://air.imag.fr/mediawiki/images/0/0a/Report_Trodometre_BJF_TB_PolytechGrenoble.pdf Score Report] and SRS


==Week 3 (02/04)==
==WEEK 2: from January 21st to January 27th==
* Meeting with tutor and BTLE study


==Week 4 (02/11) ==
* Set up Class and Activity


==Week 5 (02/18)==
==WEEK 3: from January 28th to February 3rd==
* Wahoo Sensor Implementation


==Week 6 (03/04)==
*OSM format Study
*Tutor Edit specifications
*Update Class Diagram


==Week 7 (03/18)==
==WEEK 4: from January 4th to February 10th==
*GPS Implementation
*Implementation of Coordinated Calculator
*Implementation PaserXML OSM (import / export)
* Frist Test with OutDoorMode(GPS)


== Week 8 (03/25) ==
*Gyroscope and Compas Implementation
*Frist Test with InDoorMode


== Week 9 (04/01) ==
==WEEK 5: from February 11th to February 17th==
*First Test Analyse


== Week 10 (08/01) ==
==WEEK 6: from February 18th to February 24th==
*Redefinition of the use of the compass after test
*Tests
*Interface implementation
*Bug correction
*Final Tests and Validation


==Related documents==

*[http://air.imag.fr/mediawiki/images/1/13/KickScooter.tar Code ]
==WEEK 7: from March 4th to March 10th==
*[http://air.imag.fr/mediawiki/images/5/5b/Trodom%C3%A8tre_report.pdf Report]

*[http://air.imag.fr/mediawiki/index.php/File:Diagramme_de_classe.pdf UML ]

*[http://air.imag.fr/mediawiki/images/7/76/Trodom%C3%A8tre_slides.pdf Slides ]
==WEEK 8: from March 11th to March 17th==
*[http://air.imag.fr/mediawiki/images/a/a6/Flyer_trodometre.pdf Flyers ]

Latest revision as of 20:50, 24 September 2013

Progress of the project

The project started January 21th, 2013.

Week 1 (01/21)

  • Writing Score Report and SRS

Week 2 (01/28)

Week 3 (02/04)

  • Meeting with tutor and BTLE study

Week 4 (02/11)

  • Set up Class and Activity

Week 5 (02/18)

  • Wahoo Sensor Implementation

Week 6 (03/04)

  • OSM format Study
  • Tutor Edit specifications
  • Update Class Diagram

Week 7 (03/18)

  • GPS Implementation
  • Implementation of Coordinated Calculator
  • Implementation PaserXML OSM (import / export)
  • Frist Test with OutDoorMode(GPS)

Week 8 (03/25)

  • Gyroscope and Compas Implementation
  • Frist Test with InDoorMode

Week 9 (04/01)

  • First Test Analyse

Week 10 (08/01)

  • Redefinition of the use of the compass after test
  • Tests
  • Interface implementation
  • Bug correction
  • Final Tests and Validation