Difference between revisions of "Proj-2012-2013-trodomètre"

From air
Jump to navigation Jump to search
(Created page with "=Progress of the project= The project started January 14th, 2013. ==WEEK 1: from January 14th to January 20th== ==WEEK 2: from January 21st to January 27th== ==WEEK 3: from…")
 
 
(15 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
=Progress of the project=
 
=Progress of the project=
   
The project started January 14th, 2013.
+
The project started January 21th, 2013.
   
  +
==Week 1 (01/21)==
==WEEK 1: from January 14th to January 20th==
 
  +
*Writing Score Report and SRS
   
  +
==Week 2 (01/28)==
  +
*Finishing [http://air.imag.fr/mediawiki/images/0/0a/Report_Trodometre_BJF_TB_PolytechGrenoble.pdf Score Report] and SRS
   
  +
==Week 3 (02/04)==
==WEEK 2: from January 21st to January 27th==
 
  +
* Meeting with tutor and BTLE study
   
  +
==Week 4 (02/11) ==
  +
* Set up Class and Activity
   
  +
==Week 5 (02/18)==
==WEEK 3: from January 28th to February 3rd==
 
  +
* Wahoo Sensor Implementation
   
  +
==Week 6 (03/04)==
  +
*OSM format Study
  +
*Tutor Edit specifications
  +
*Update Class Diagram
   
  +
==Week 7 (03/18)==
==WEEK 4: from January 4th to February 10th==
 
  +
*GPS Implementation
  +
*Implementation of Coordinated Calculator
  +
*Implementation PaserXML OSM (import / export)
  +
* Frist Test with OutDoorMode(GPS)
   
  +
== Week 8 (03/25) ==
  +
*Gyroscope and Compas Implementation
  +
*Frist Test with InDoorMode
   
  +
== Week 9 (04/01) ==
==WEEK 5: from February 11th to February 17th==
 
  +
*First Test Analyse
   
  +
== Week 10 (08/01) ==
==WEEK 6: from February 18th to February 24th==
 
  +
*Redefinition of the use of the compass after test
  +
*Tests
  +
*Interface implementation
  +
*Bug correction
  +
*Final Tests and Validation
   
  +
==Related documents==
 
  +
*[http://air.imag.fr/mediawiki/images/1/13/KickScooter.tar Code ]
==WEEK 7: from March 4th to March 10th==
 
  +
*[http://air.imag.fr/mediawiki/images/5/5b/Trodom%C3%A8tre_report.pdf Report]
 
  +
*[http://air.imag.fr/mediawiki/index.php/File:Diagramme_de_classe.pdf UML ]
 
  +
*[http://air.imag.fr/mediawiki/images/7/76/Trodom%C3%A8tre_slides.pdf Slides ]
==WEEK 8: from March 11th to March 17th==
 
  +
*[http://air.imag.fr/mediawiki/images/a/a6/Flyer_trodometre.pdf Flyers ]

Latest revision as of 22:50, 24 September 2013

Progress of the project

The project started January 21th, 2013.

Week 1 (01/21)

  • Writing Score Report and SRS

Week 2 (01/28)

Week 3 (02/04)

  • Meeting with tutor and BTLE study

Week 4 (02/11)

  • Set up Class and Activity

Week 5 (02/18)

  • Wahoo Sensor Implementation

Week 6 (03/04)

  • OSM format Study
  • Tutor Edit specifications
  • Update Class Diagram

Week 7 (03/18)

  • GPS Implementation
  • Implementation of Coordinated Calculator
  • Implementation PaserXML OSM (import / export)
  • Frist Test with OutDoorMode(GPS)

Week 8 (03/25)

  • Gyroscope and Compas Implementation
  • Frist Test with InDoorMode

Week 9 (04/01)

  • First Test Analyse

Week 10 (08/01)

  • Redefinition of the use of the compass after test
  • Tests
  • Interface implementation
  • Bug correction
  • Final Tests and Validation

Related documents