Fiche - Tachymètre: Difference between revisions
Jump to navigation
Jump to search
Regis.Ramel (talk | contribs) |
|||
| (26 intermediate revisions by 2 users not shown) | |||
| Line 1: | Line 1: | ||
= |
= Project team = |
||
* MACE Quentin |
|||
== Semaine 1 : 18 Janvier - 24 Janvier == |
|||
* NOUGUIER Thibaut |
|||
* Choix du projet |
|||
* RAMEL Régis |
|||
* Présentation de Cohorte par Oliver Gattaz et Bassem Debbabi |
|||
* Tuteur : Olivier Gattaz |
|||
= Project progress = |
|||
== Semaine 2 : 25 Janvier - 31 Janvier == |
|||
== Week 1 : 11/01 - 17/01 == |
|||
* Découverte du projet |
|||
Work done : |
|||
* Installation de Cohorte |
|||
* Choice of the project |
|||
* Détermination des exigences fonctionnelles et non fonctionnelles |
|||
* Presentation of Cohorte by Olivier Gattaz and Bassem Debbabi |
|||
* [[SRS_-_Tachymètre | '''SRS''']] |
|||
== |
== Week 2 : 18/01 - 24/01 == |
||
Work done : |
|||
== Semaine 4 : 8 Février - 14 Février == |
|||
* Discover of the project environment |
|||
== Semaine 5 : 15 Février - 21 Février == |
|||
* Installation of Cohorte tools |
|||
== Semaine 6 : 22 Février - 28 Février == |
|||
* Definition of functional and non-functional requirements |
|||
== Semaine 7 : 29 Février - 6 Mars == |
|||
* Writing of the SRS |
|||
== Semaine 8 : 7 Mars - 13 Mars == |
|||
== Semaine 9 : 14 Mars - 20 Mars == |
|||
== |
== Week 3 : 25/01 - 31/01 == |
||
Work done : |
|||
== Semaine 11 : 28 Mars - 3 Avril == |
|||
* Cohorte tutorial done |
|||
== Semaine 12 : 4 - 6 Avril == |
|||
* Realisation of UML diagrams |
|||
== Week 4 : 01/02 - 07/02 == |
|||
Work done : |
|||
* Meeting at Isandlatech with Olivier Gattaz |
|||
* Study of the Doppler effect |
|||
* Simulations of speed calculations based on the frequency |
|||
* Starting the project with Cohorte |
|||
== Week 5 : 08/02 - 14/02 == |
|||
Work done : |
|||
* Meeting at Isandlatech with Olivier Gattaz |
|||
* Working on the component diagram |
|||
* Working on the web client’s structure |
|||
* Definition of processed data and synthetic data |
|||
* Tasks repartition |
|||
* Working on use case |
|||
== Week 6 : 15/02 - 21/02 == |
|||
Work done : |
|||
* Meeting at Isandlatech with Olivier Gattaz |
|||
* Working on Cohorte : Specification of components an application’s structure |
|||
* Working on wiring the sensor |
|||
* Working on connecting the Raspberry Pi (many fails) |
|||
Problems : |
|||
* Confusion between our Raspberry and Isandlatech’s |
|||
* SD carte troubleshooting, impossible to install raspbian |
|||
== Week 7 : 22/02 - 28/02 == |
|||
Work done : |
|||
* Holidays |
|||
* Tries to install raspbian on the Raspberry (fail) |
|||
== Week 8 : 29/02 - 06/03 == |
|||
Work done : |
|||
* Installation of raspbian on the Raspberry |
|||
* Working on the 7th march presentation |
|||
Problems : |
|||
* An Arduino is needed to acquire measures from the HB100 |
|||
== Week 9 : 07/03 - 13/03 == |
|||
Work done : |
|||
* 7th march presentation |
|||
* Working on the web interface |
|||
* Meeting at Isandlatech with Olivier Gattaz |
|||
* Working on the connection Raspberry – Arduino |
|||
* Working on the connection Arduino – HB100 |
|||
* Connexion between Arduino and a PC established |
|||
* Working on returning and displaying measures from the sensor |
|||
== Week 10 : 14/03 - 20/03 == |
|||
Work done : |
|||
* Working on the transmission of data between the Arduino and the Raspberry |
|||
* Working on the data process |
|||
* Working on the web interface |
|||
* Working on the Raspberry components |
|||
* Meeting at Isandlatech with Olivier Gattaz |
|||
* Tests with a car around Isandlatech |
|||
* Creation of a tube to lead the sensor waves |
|||
* Working on Cohorte components |
|||
Problems : |
|||
* Impossible to get speed measures over than 25 km/h |
|||
== Week 11 : 21/03 - 27/03 == |
|||
Work done : |
|||
* Discover of the need to build an amplification circuit |
|||
* Working on the connection between the different Cohorte components |
|||
* Working on the report |
|||
Problems : |
|||
* Problems with the integration of Cohorte components in the application |
|||
== Week 12 : 28/03 - 03/04 == |
|||
Work done : |
|||
* Working on connecting between the different Cohorte components |
|||
* Working on transmitting data from the sensor to the server |
|||
* Working on the report |
|||
* Working on “Échantillonneur” and “Élaborateur” components |
|||
Problems : |
|||
* Problems with the dependances between components |
|||
== Week 13 : 04/04 - 06/04 == |
|||
Work done : |
|||
* Finalization of the application |
|||
* Working on the Flyer |
|||
* Working on the presentation |
|||
* Finalization of the report |
|||
Latest revision as of 16:24, 5 April 2016
Project team
- MACE Quentin
- NOUGUIER Thibaut
- RAMEL Régis
- Tuteur : Olivier Gattaz
Project progress
Week 1 : 11/01 - 17/01
Work done :
- Choice of the project
- Presentation of Cohorte by Olivier Gattaz and Bassem Debbabi
Week 2 : 18/01 - 24/01
Work done :
- Discover of the project environment
- Installation of Cohorte tools
- Definition of functional and non-functional requirements
- Writing of the SRS
Week 3 : 25/01 - 31/01
Work done :
- Cohorte tutorial done
- Realisation of UML diagrams
Week 4 : 01/02 - 07/02
Work done :
- Meeting at Isandlatech with Olivier Gattaz
- Study of the Doppler effect
- Simulations of speed calculations based on the frequency
- Starting the project with Cohorte
Week 5 : 08/02 - 14/02
Work done :
- Meeting at Isandlatech with Olivier Gattaz
- Working on the component diagram
- Working on the web client’s structure
- Definition of processed data and synthetic data
- Tasks repartition
- Working on use case
Week 6 : 15/02 - 21/02
Work done :
- Meeting at Isandlatech with Olivier Gattaz
- Working on Cohorte : Specification of components an application’s structure
- Working on wiring the sensor
- Working on connecting the Raspberry Pi (many fails)
Problems :
- Confusion between our Raspberry and Isandlatech’s
- SD carte troubleshooting, impossible to install raspbian
Week 7 : 22/02 - 28/02
Work done :
- Holidays
- Tries to install raspbian on the Raspberry (fail)
Week 8 : 29/02 - 06/03
Work done :
- Installation of raspbian on the Raspberry
- Working on the 7th march presentation
Problems :
- An Arduino is needed to acquire measures from the HB100
Week 9 : 07/03 - 13/03
Work done :
- 7th march presentation
- Working on the web interface
- Meeting at Isandlatech with Olivier Gattaz
- Working on the connection Raspberry – Arduino
- Working on the connection Arduino – HB100
- Connexion between Arduino and a PC established
- Working on returning and displaying measures from the sensor
Week 10 : 14/03 - 20/03
Work done :
- Working on the transmission of data between the Arduino and the Raspberry
- Working on the data process
- Working on the web interface
- Working on the Raspberry components
- Meeting at Isandlatech with Olivier Gattaz
- Tests with a car around Isandlatech
- Creation of a tube to lead the sensor waves
- Working on Cohorte components
Problems :
- Impossible to get speed measures over than 25 km/h
Week 11 : 21/03 - 27/03
Work done :
- Discover of the need to build an amplification circuit
- Working on the connection between the different Cohorte components
- Working on the report
Problems :
- Problems with the integration of Cohorte components in the application
Week 12 : 28/03 - 03/04
Work done :
- Working on connecting between the different Cohorte components
- Working on transmitting data from the sensor to the server
- Working on the report
- Working on “Échantillonneur” and “Élaborateur” components
Problems :
- Problems with the dependances between components
Week 13 : 04/04 - 06/04
Work done :
- Finalization of the application
- Working on the Flyer
- Working on the presentation
- Finalization of the report