Proj-2012-2013-trodomètre: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
| Line 1: | Line 1: | ||
=Progress of the project= |
=Progress of the project= |
||
The project started January |
The project started January 21th, 2013. |
||
==Week 1 (01/ |
==Week 1 (01/21)== |
||
*Writing Score Report and SRS |
|||
| ⚫ | |||
*Writing Score Report and SRS |
|||
==Week |
==Week 3 (02/04)== |
||
* Meeting with tutor and BTLE study |
|||
==Week |
==Week 4 (02/11) == |
||
* Set up Class and Activity |
|||
| ⚫ | |||
* Wahoo Captor Implementation |
|||
==Week |
==Week 6 (03/04)== |
||
*OSM format Study |
|||
*Tutor Edit specifications |
|||
*Update Class Diagram |
|||
| ⚫ | |||
*GPS Implementation |
|||
*Implementation of Coordinated Calculator |
|||
*Implementation PaserXML OSM (import / export) |
|||
* Frist Test with OutDoorMode(GPS) |
|||
==Week |
== Week 8 (03/25) == |
||
*Gyroscope and Compas Implementation |
|||
*Frist Test with InDoorMode |
|||
| ⚫ | |||
| ⚫ | |||
| ⚫ | |||
Revision as of 09:24, 25 March 2013
Progress of the project
The project started January 21th, 2013.
Week 1 (01/21)
- Writing Score Report and SRS
Week 2 (01/28)
- Writing Score Report and SRS
Week 3 (02/04)
- Meeting with tutor and BTLE study
Week 4 (02/11)
- Set up Class and Activity
Week 5 (02/18)
- Wahoo Captor Implementation
Week 6 (03/04)
- OSM format Study
- Tutor Edit specifications
- Update Class Diagram
Week 7 (03/18)
- GPS Implementation
- Implementation of Coordinated Calculator
- Implementation PaserXML OSM (import / export)
- Frist Test with OutDoorMode(GPS)
Week 8 (03/25)
- Gyroscope and Compas Implementation
- Frist Test with InDoorMode