Difference between revisions of "Project 2014-2015-CannonBall/Scrum"
Jump to navigation
Jump to search
Line 23: | Line 23: | ||
|- |
|- |
||
!scope="row"| 1 |
!scope="row"| 1 |
||
− | | The RICM want the car works in order to start the project. |
+ | | The RICM want the car works in order to start the project. ( 6 ) |
| 34 |
| 34 |
||
| 1 week |
| 1 week |
||
Line 29: | Line 29: | ||
|- |
|- |
||
!scope="row"| 2 |
!scope="row"| 2 |
||
− | | The RICM must master the different technologies to be able to do the project. |
+ | | The RICM must master the different technologies to be able to do the project. ( 4 ) |
| 34 |
| 34 |
||
| all time |
| all time |
||
Line 35: | Line 35: | ||
|- |
|- |
||
!scope="row"| 3 |
!scope="row"| 3 |
||
− | | The researcher must be able to consult in real time the car's information to make changes if needed. |
+ | | The researcher must be able to consult in real time the car's information to make changes if needed. ( 5 ) |
| 21 |
| 21 |
||
| 2 weeks |
| 2 weeks |
||
Line 41: | Line 41: | ||
|- |
|- |
||
!scope="row"| 4 |
!scope="row"| 4 |
||
− | | The developer have to optimize the processing speed to provide a better product experience. |
+ | | The developer have to optimize the processing speed to provide a better product experience. ( 2 ) |
| 21 |
| 21 |
||
| 1 week |
| 1 week |
||
Line 47: | Line 47: | ||
|- |
|- |
||
!scope="row"| 5 |
!scope="row"| 5 |
||
− | | The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm). |
+ | | The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm). ( 1 ) |
| 13 |
| 13 |
||
| |
| |
||
Line 53: | Line 53: | ||
|- |
|- |
||
!scope="row"| 6 |
!scope="row"| 6 |
||
− | | The researcher must be able to change the vehicle mode to realize different tests. |
+ | | The researcher must be able to change the vehicle mode to realize different tests. ( 3 ) |
| 8 |
| 8 |
||
| 3 weeks |
| 3 weeks |
||
Line 59: | Line 59: | ||
|- |
|- |
||
|} |
|} |
||
+ | |||
+ | =First speed= |
||
+ | We need to do the tasks 6, 5 and 2 |
||
=Waffle= |
=Waffle= |
Revision as of 16:02, 10 February 2015
User stories
1. The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm).
2. The developer have to optimize the processing speed to provide a better product experience.
3. The researcher must be able to change the vehicle mode to realize different tests.
4. The RICM must master the different technologies to be able to do the project.
5. The researcher must be able to consult in real time the car's information to make changes if needed.
6. The RICM want the car works in order to start the project.
Product backlog
User story | Priority | Time | Actors | |
---|---|---|---|---|
1 | The RICM want the car works in order to start the project. ( 6 ) | 34 | 1 week | |
2 | The RICM must master the different technologies to be able to do the project. ( 4 ) | 34 | all time | all |
3 | The researcher must be able to consult in real time the car's information to make changes if needed. ( 5 ) | 21 | 2 weeks | |
4 | The developer have to optimize the processing speed to provide a better product experience. ( 2 ) | 21 | 1 week | |
5 | The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm). ( 1 ) | 13 | ||
6 | The researcher must be able to change the vehicle mode to realize different tests. ( 3 ) | 8 | 3 weeks |
First speed
We need to do the tasks 6, 5 and 2