1. The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm).
1. Control algorithm.
 
   
 
2. The developer have to optimize the processing speed to provide a better product experience.
 
2. The developer have to optimize the processing speed to provide a better product experience.

Revision as of 15:51, 10 February 2015

User stories

1. The researcher must be able to send a line of instruction for verify the good behavior of the car (Control Algorithm).

2. The developer have to optimize the processing speed to provide a better product experience.

3. The researcher must be able to change the vehicle mode to realize different tests.

4. The RICM must master the different technologies to be able to do the project.

5. The researcher must be able to consult in real time the car's information to make changes if needed.

6. The RICM want the car works in order to start the project.

Product backlog

User story Priority Time Actors
1 The RICM want the car works in order to start the project. 34 1 week
2 The RICM must master the different technologies to be able to do the project. 34 all time all
3 The researcher must be able to consult in real time the car's information to make changes if needed. 21 2 weeks
4 The developer have to optimize the processing speed to provide a better product experience. 21 1 week
5 Control algorithm. 13
6 The researcher must be able to change the vehicle mode to realize different tests. 8 3 weeks

Waffle