RICM4 2017 2018 - Dashboard
Jump to navigation
Jump to search
Presentation
The aim of DashBoard is to update a single page application already existing. It allows OAR's users and managers to use the technology more comfortably. Unfortunatly the 5th version of Angular made it impossible to use because technologies incompatibilities.
Contraints
- SB Admin Angular5 based
- Single-page application
- Restful service
Team
Students:
- BELGUENDOUZ Sekina : Developer
- LARNICOL Titouan : Project leader
Supervisor :
- RICHARD Olivier
Progress
Week 0 : 15/01/18
- Projects' choice
Week 1 : 22/01/18
Work done
- Read the documentation.
- Get familiar with the technological constraints.
Week 2 : 29/01/18
Work done
- Read the documentation.
- Get familiar with the technological constraints.
Week 3 : 05/02/18
Work done
- Creation of the Git deposit
- Decision on the general outline of our SPA
- Start the template
To do for next week
- Finish the outline of the wed application
Week 4 : 12/02/18
Work done
- Work on the template
- Look at the usage of the API
- Download OAR docker
To do for next week
- Finish roughly the template
- Try to use the API with some commands
Week 5 : 19/02/18
Work done
- Work on the outline
- Try to solve the problem related to the API
To do for next week
- Finish roughly the template
- Try to use the API with some commands
Week 6 : 26/02/18
Work done
- Finish roughly the template
- Solve the problem related to the API with the supervisor
To do for next week
- Try to use the API with some commands
Week 7 : 05/03/18
Work done
- Do the steps given by the supervisor to use the API with SB-Admin-BS4-Angular-5
- Start to talk about the presentation
To do for next week
- Prepare the presentation
Week 8 : 12/03/18
After the presentation, we realised we were on the wrong path. We finally understood what was our project's goal: not to create but to update an existing SPA.
Work done
- Talk with our supervisor to have more explanation.
- Try to make oardocker work with him.
To do for next week
- Try to make our first call to the API
Week 9 : 19/03/18
Work done
- Try to make the enviromment work with our supervisor.
To do for next week
- Try to solve the problem of cross-domain
Week 10 : 26/03/18
Work done
- Try to create jobs with our supervisor.
To do for next week
- Try to get use to the json format
Week 11 : 02/04/18
To do
- Login page
- Resources and jobs' listing
- Creation of resources and jobs
- GL docs
To do for next week
- Prepare the presentation and rapport