Théo and Nicolas tried the cards,the sensors and |
Théo and Nicolas tried the cards,the sensors and the LoRa plug-in thanks to the basic programs and the previous project programs. |
||
They also started the main program witch mesure the temperature and send it via the LoRa plug-in. |
|||
=== |
===Work session content=== |
||
*Creation of a previsional schedule |
|||
*Décision de créer un diagramme de Gantt (tableau prévisionnel) |
|||
=== |
===Visitation of the farm=== |
||
Revision as of 15:52, 16 November 2017
<< Previous week report | Back to project | Next week report >>
Work session 4 : report - 09/11/2017
Progress during holidays
Théo and Nicolas tried the cards,the sensors and the LoRa plug-in thanks to the basic programs and the previous project programs. They also started the main program witch mesure the temperature and send it via the LoRa plug-in.
Work session content
- Creation of a previsional schedule