Projets-2015-2016-DashBoard: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
Line 42: | Line 42: | ||
== Week 5 (February 08th - February 14th) == |
== Week 5 (February 08th - February 14th) == |
||
We have done technological watch on OAR docker |
We have done technological watch on OAR docker. |
||
== Week 6 (February 15th - February 21st) == |
== Week 6 (February 15th - February 21st) == |
||
We started doing SB Admin's tests to understand how it works. |
|||
== Week 7 (February 29th - March 06th) == |
== Week 7 (February 29th - March 06th) == |
||
We continue to do tests on SB Admin. |
|||
== Week 8 (March 07th - March 13th) == |
== Week 8 (March 07th - March 13th) == |
Revision as of 13:21, 7 March 2016
Preambule
Project presentation
Team
- Supervisors : Olivier Richard
- Members : Matthieu CROUZET, Tanguy MATHIEU
- Departement : RICM 4, Polytech Grenoble
Progress of the project
The project started January 11th, 2015.
Week 1 (January 11h - January 17th)
- Project choice
Week 2 (January 18th - January 24th)
- Project exploration
- SRS sheet
Week 3 (January 25th - January 31st)
- Use Case Diagram
Week 4 (February 01 - February 07th)
We looked over documentation SB Admin v2.0 to have a better interpretation than what we have to do in our project.
Week 5 (February 08th - February 14th)
We have done technological watch on OAR docker.
Week 6 (February 15th - February 21st)
We started doing SB Admin's tests to understand how it works.
Week 7 (February 29th - March 06th)
We continue to do tests on SB Admin.